High School Construction Update #6

Over the past few weeks, repairs to the existing tennis courts were made and final finishes are
being applied. The second turf field lights are installed and field turf for this field will be
installed next week. Work on the retaining wall continues. The installation of the track surface
and stadium turf will be underway in late August. Substantial completion of the project is still
on time for March 2018 when the auxiliary gymnasium will be completed.
 
 
 An overview of the project is available at this link: https://www.umtsd.org/Page/5304  


Review all High School updates here

 

Middle School Construction Update #15

Construction work on the interior and exterior of the Middle School continues. Over the past two weeks, work continues on the installation of floors and ceilings throughout the building. Preliminary work for the installation of lockers has begun. The installation of casework in the Science classrooms began this week and will continue through August. The completion of the drainage system and soil amendments for the tennis courts will be followed by paving at the end of August. Storm piping, underground work, backfill and grading will continue on the track and field through the end of July. The project continues on time with substantial completion in August 2017.

 
 
 
 
Questions regarding the project can be directed to the Business Manager at 215-830-1505.