Return to Headlines

High School & Middle School Construction Information

 

 
High School Construction Update #3

The National Pollutant Discharge Elimination System permit was issued on April 26, 2017.  This milestone which required collaboration between the School District and the Montgomery County Conservation District ensured the project could begin on schedule.  On May 5, 2017, Upper Moreland Township issued a grading permit for the project.  On May 8, work began on site.  Field work is scheduled to be completed in September with a current timeline as follows:

  • July: Tennis court completion (sealing of courts)
  • August: Second turf field as well as the grass practice field, baseball and softball fields will be completed
  • September: the football field and track will be completed
  • November: Field House (bathrooms, concessions and storage) will be completed
  • April 2018: Auxiliary Gym will be completed

Upon completion, natural fields will require time for grass to stabilize and meet the standard in the specifications before use can begin. 

 

  An overview of the project is available at this link: https://www.umtsd.org/Page/5304  


Review all High School updates here

 
Middle School Construction Update #12 

The water meter pit and piping installation on the front of the building has been completed.  Upper Moreland Township has issued a grading permit and site work will begin on the fields.  Corridor door frames throughout the building are being installed.  The offices and support areas of the media center, the television studio and two other new classrooms have been substantially completed. Work began this week on vacated classroom renovations and to provide exterior egress.
 
 
 
Questions regarding the project can be directed to the Business Manager at 215-830-1505.



CLOSE